UPDATED CONTRACT
This commit is contained in:
parent
64f30aa363
commit
f816d3eef4
@ -239,19 +239,18 @@ The following Exhibits are attached hereto and incorporated by reference into th
|
||||
|
||||
**IN WITNESS WHEREOF,** the Parties hereto have caused this Software Development and Implementation Agreement to be executed by their duly authorized representatives as of the Effective Date.
|
||||
|
||||
**[CLIENT COMPANY NAME]**
|
||||
**[CLIENT COMPANY: Western Institute of Technology]**
|
||||
|
||||
By: \_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_
|
||||
Name: \_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_
|
||||
Title: \_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_
|
||||
Date: \_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_
|
||||
Name: Mark Glen C. Guides
|
||||
Date: 08/04/2025
|
||||
|
||||
**[YOUR COMPANY NAME]** (Developer)
|
||||
**[CELL TECH]** (Developer)
|
||||
|
||||
By: \_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_
|
||||
Name: \_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_
|
||||
Title: \_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_
|
||||
Date: \_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_\_
|
||||
Name: Jose DanielG. Percy
|
||||
|
||||
Name: Rekcel M. Endencia
|
||||
|
||||
Date: 08/04/2025
|
||||
|
||||
---
|
||||
|
||||
@ -400,13 +399,13 @@ gantt
|
||||
Final Documentation & Handover :handover, after admintrain, 10d
|
||||
|
||||
%% Milestones (Aligned with phase ends where logical)
|
||||
milestone Phase 1 Complete : 2024-02-16
|
||||
milestone Core Backend Complete : 2024-04-19
|
||||
milestone Core Frontend Complete : 2024-05-31
|
||||
milestone Development Complete : 2024-07-26
|
||||
milestone Testing Complete : 2024-08-23
|
||||
milestone Project Go-Live : 2024-08-30
|
||||
milestone Project Handover : 2024-09-27
|
||||
milestone Phase 1 Complete : 2025-02-16
|
||||
milestone Core Backend Complete : 2025-04-19
|
||||
milestone Core Frontend Complete : 2025-05-31
|
||||
milestone Development Complete : 2025-07-26
|
||||
milestone Testing Complete : 2025-08-23
|
||||
milestone Project Go-Live : 2025-08-30
|
||||
milestone Project Handover : 2025-09-27
|
||||
```
|
||||
|
||||
*Note: Dates are estimates and subject to refinement based on detailed sprint planning and potential scope adjustments defined via the Change Management process (Article 6).*
|
||||
|
||||